				 Products 
				- Pipe Support Systems
                    
 
		
		 
		
		 
                     
                     
				  | 
			 
			
				| 
				
				 | 
			 
		 
		
		
			
				|  
				 | 
			 
			
				| 
				 PS/PSE Installation 
				Procedure  | 
				
				 
				   | 
			 
			
				
				
					- 
					
Scrape off loose gravel, if gravel exists.  
					- 
					
Consult manufacturer of existing or new 
					roofing system as to type of walk pads required for their 
					roofing system.  
					- 
					
After pads are installed, place bases on 
					pads  
					- 
					
Place frames over pipe to support and insert 
					in bases  
					- 
					
Fasten frames to bases with supplied bolt & 
					nut.  
					- 
					
With all pipe supports in place, start at 
					beginning of system and adjust each strut/roller to achieve 
					a balanced system. The process should be done in stages, 
					raising the pipe ½" at a time. When desired height is 
					reached, check each support to determine if and equal amount 
					of weight is being distributed at each support.  
					- 
					
Installation per local, provincial or state 
					Plumbing & Gas Code.  
				 
					 | 
				
				 
				
				  
				
				   | 
			 
			
				
				
					
						
						  | 
						  | 
						
						  | 
						  | 
						
						  | 
					 
					
						| PS-1-2 | 
						  | 
						PSE-2-2 | 
						  | 
						PSE-Custom | 
					 
				 
				 | 
			 
		 
		  
		 | 
	 
	
		
		   | 
	 
 
 | 
  |